Short answer: if your shed is over 30m², you almost certainly need building consent. Sheds under 30m² can be exempt, but only if they meet specific conditions, and rural sheds and hay barns up to 110m² have their own exemption. Every exemption still requires the building to meet the Building Code and your district plan.
For context, a basic 8m x 10m Wide Span shed is 80m², so nearly every shed we build goes through consent. We handle that process for you.
When is a shed exempt from building consent?
Under Schedule 1 of the Building Act, a single-storey detached shed is exempt if:
- The floor area is 30m² or less
- It has no kitchen or bathroom (plumbing still needs consent, electrical needs a registered electrician)
- A kitset is designed or reviewed by a Chartered Professional Engineer, or the build is designed or supervised by a Licensed Building Practitioner
- It meets the boundary setback rules below
You can still build an exempt shed yourself using lightweight materials, as long as the structure follows the Building Code's acceptable solution.
How close to the boundary can I build a shed?
The rules changed in October 2025:
| Shed size | Minimum distance from boundary or other buildings |
|---|
| Under 10m² | No setback required |
| 10m² to 30m² | 1 metre |
| Over 30m² | Needs building consent; district plan setbacks apply |
Before October 2025, a shed had to sit at least as far from the boundary as it was tall. That rule is gone for exempt buildings, but your district plan may still set its own boundary, height and recession plane rules. Check those before you pick a spot.
Do farm sheds need building consent?
Single-storey sheds and hay barns in rural zones are exempt up to 110m², as long as a Chartered Professional Engineer designs or reviews them, or a Licensed Building Practitioner designs or supervises the build.
The exemption wording refers to "pole sheds and hay barns". Despite the name, "pole shed" is the general term councils use, and it covers steel-framed sheds too, so a steel shed can qualify under the same 110m² exemption. Most working farm sheds are well over 110m² anyway: for example, our Multi Purpose farm shed is 18m x 22.5m, or 405m².
What about carports and garages?
- Carports up to 40m² are exempt with engineer or LBP involvement.
- Garages fall under the 30m² shed rule. A standard double garage (6m x 6m) is 36m², so it needs consent.
Building consent vs resource consent: what's the difference?
- Building consent confirms the building is safe and meets the Building Code. Issued by your council under the Building Act.
- Resource consent confirms the building fits your district plan: height, site coverage, setbacks, zoning. Issued under the Resource Management Act.
An exempt shed can still need resource consent if it breaks a district plan rule. A consented shed can need both.
How long does building consent take for a shed?
Councils must process building consent within 20 working days. The clock stops each time council requests more information, so a complete application matters.
How much does building consent cost?
Fees vary by council and project value, and can range from around $1,000 for simple, smaller structures up to $5,000+ for commercial buildings. Engineering and site-specific design add to this. Wide Span Sheds includes consent management in every build quote, so you see the full figure up front.
What happens if I build a shed without consent?
Council can issue a notice to fix, require changes or removal, and impose fines. Unconsented buildings can also cause problems with insurance claims and when you sell, because they show up on the LIM report.
How Wide Span Sheds handles consent
- Site-specific engineering for your wind zone, snow load and ground conditions
- Consent drawings and application prepared and lodged for you
- Council requests for information handled by our team
- Built by Cohesive Construction, so the build matches what was consented
Get a quote and we'll confirm whether your shed needs consent at your address.